Hello. There was no Week 27 due to Easter, but we’re back with the best of the action from this week’s work.
Our thanks (as always) go to Dave Clark, Site Manager (& Chief Photographer) for John Turner Construction Ltd.

New floor boards have been laid in the areas where dry rot had caused significant damage. This photo shows the area to the right of the altar.

It’s been a while since we had a photo of a hole, so this shot made me nostalgic. This photo captures the connection of the new incoming electric mains on the footpath by the school on Lugsdale Road.

The extension is really starting to take shape. Note the feature vertical zinc cladding.

The floor boards were completely removed to allow the cleaning out of the floor void in order to relay the existing floorboards along with new which eventually shall be sanded, stained and re-varnished.