The best of this week’s action captured by Dave Clark from John Turner Construction Ltd.

A buttress on top of the arch had to come out for the layout of the new extension. In order for it’s safe removal a flying shoring scaffold design had to be installed to support the corner of the church in order to remove the masonry and archway and then a new foundation was installed to rebuild a full height corner buttress.

A look into the existing adopted manhole. Or a inspection chamber if you prefer. All the new foul and surface water from the church building and new car park was connected into this.